Project Drivers & Goals
The Schrenk East Renovation is the final step in the renewal Master Plan for the Schrenk complex. The primary project driver is to improve and increase research laboratory space to support the growth of both the Biological Sciences and Chemistry Departments at Missouri S&T, while improving teaching labs, office space, and the overall facility condition of an aging facility on campus. These improvements and the resulting growth in enrollment and retention will contribute to the University’s 2030 North Star Goals: Attain Carnegie R1 Classification, Grow enrollment to 12,000 students, and Achieve a Top 100 Ranking.
Project Goals
Project Schedule
A summary of the proposed project schedule is outlined below. A detailed project schedule is included
in Chapter 05 of this document.
Project Budget
The project will be delivered using a construction manager at risk (CMAR) delivery process. The total
construction cost assessed for the project is $31,600,000. At the time of this report, Phase 1A and 1B
has been established at $23,028,10. The detailed project opinion of cost is included in Chapter 05 of this
document.
View of Schrenk Hall from the East
Auditorium View
Lobby View
View of Schrenk Hall from the South
Project Schedule
A summary of the proposed project schedule is outlined below. A detailed project schedule is included
in Chapter 05 of this document.
Project Budget
The project will be delivered using a construction manager at risk (CMAR) delivery process. The total
construction cost assessed for the project is $31,600,000. At the time of this report, Phase 1A and 1B
has been established at $23,028,10. The detailed project opinion of cost is included in Chapter 05 of this
document.